Traffic misery at Swallow Roundabout expected as FIVE MONTHS of roadworks planned


Works worth some £2.2 million are planned to start in late November.

Previous roadworks on the A90 near the Invergowrie junction.

Previous roadworks on the A90 near the Invergowrie junction. Image: Kim Cessford/DC Thomson

Drivers could face traffic misery at the Swallow Roundabout as five months of roadworks take place on the A90 near Invergowrie.

Amey will carry out a series of resurfacing and drainage improvement works on the A90 approach to Swallow Roundabout from Monday November 23.

The £2.2 million project is scheduled to run until May 6 2027, and will address ongoing flooding issues on the stretch of road.

Resurfacing and barrier improvement works will also take place.

Amey says the majority of the roadworks will be carried out overnight to minimise disruption on the busy route.

The location of the A90 roadworks close to the Swallow Roundabout

The location of the A90 roadworks close to the Swallow Roundabout. Image: Amey

Additionally, there will be no restrictions on the A90 between Sunday 20 December and 6.30am on Monday 11 January. 

However, there will be lane closures on both carriageways from January 11 to February 11, which could cause significant delays at the Swallow Roundabout.

A full timeline of the planned traffic management is below:

Disruption during A90 Invergowrie roadworks

  • November 23 to May 6 – Invergowrie Roundabout and A90 slip roads: 24/7 lane closure in place.
  • November 23 to December 6 – A90 southbound: overnight lane 1 closure, 7.30pm to 6.30am.
  • December 7 to December 13 – A90 southbound: overnight road closures, 7.30pm to 6.30am (traffic diverted via Invergowrie Roundabout and slip roads).
  • December 14 to December 20 – A90 northbound: overnight lane 1 closure, 7.30pm to 6.30am.
  • December 20 to January 11 – A90 mainline (both directions): no roadworks or traffic management. Invergowrie Roundabout and slip road lane closures remain in place.
  • January 11 to February 11 – A90 northbound and southbound: continuous lane 2 closures.
  • February 14 to February 23 – A90 northbound: overnight convoy operation, 7.30pm to 6.30am.
  • February 24 to February 25 – A90 northbound and southbound: continuous lane 2 closures.
  • February 28 to May 6 – A90 northbound and southbound: overnight lane closures, 7.30pm to 6.30am (lane 1 or lane 2 depending on works).
  • May 6 – all temporary traffic management removed by 7.30pm.

According to Amey, the roadworks will benefit more than 40,000 drivers who use the busy section of the A90 each day.

Additional maintenance will also be undertaken during the programme, including the replacement of road signs, bollards and the central reserved-chip surfacing.

Resurfacing works on a section of the A90 northbound near St Madoes is already underway.

Approximately 1300 metres of the road will be resurfaced between Kinfauns and St. Madoes with overnight lane restrictions in place until Friday December 4.